The AIA G702 (Application and Certificate for Payment) and G703 (Continuation Sheet) are industry-standard forms used in construction payment applications. These forms help contractors, subcontractors, and project owners manage progress payments efficiently and transparently.

  1. G702 – Application and Certificate for Payment
    • Acts as a formal payment request from the contractor to the owner or lender.
    • Summarizes the total contract value, previous payments, current work completed, and retainage.
    • Requires certification (approval) by the architect or owner before funds are released.
  2. G703 – Continuation Sheet
    • Serves as a detailed breakdown of the work completed.
    • Lists each work item, percentage completed, amount previously billed, and remaining balance.
    • Supports the G702 by providing transparency into project progress.

Together, these forms ensure that contractors are paid fairly and on time while giving owners a clear view of work progress.


Standardized & Recognized Across the Industry

  • The American Institute of Architects (AIA) developed these forms, making them widely accepted in commercial construction.
  • Many lenders, government agencies, and large developers require these forms for processing payments.

How the Process Works

  1. The contractor fills out the G702 and G703 forms, detailing work completed and costs.
  2. The architect or project owner reviews the forms to verify progress.
  3. Once approved, payment is released based on the approved amount.

Common Mistakes & How to Avoid Them

🚫 Incorrect Retainage Calculation → Always double-check the percentage held back.
🚫 Not Signing the G702 Form → Missing signatures can delay approval.
🚫 Overbilling or Underbilling → Ensure that billed amounts match actual progress.

📌 Step-by-Step Guide to Filling Out G702 & G703 Forms (AIA Payment Application)

Properly completing G702 (Application and Certificate for Payment) and G703 (Continuation Sheet) is crucial to ensuring timely and accurate payment for work completed on a construction project. Below is a detailed step-by-step guide to filling out each section of these forms.


📝 Step 1: Filling Out the G702 Form (Application for Payment)

The G702 form serves as a summary of the payment request and must be signed before submission.


📍 Section 1: Project & Contractor Information

Project Name → Enter the official project title as stated in the contract.
Project Number → Use the reference number assigned to the project.
To Owner → Enter the name and address of the project owner.
From Contractor → List the name and address of your company.
Application Number → Sequential numbering (e.g., first request = #1, second request = #2, etc.).
Period To → The cutoff date for work covered in this payment request.


📍 Section 2: Payment Breakdown

Line ItemWhat to Enter
Contract SumTotal contract amount as per the signed agreement.
Net Change by Change OrdersSum of all approved change orders (positive or negative).
Total Contract Sum to DateContract Sum + Net Change by Change Orders.
Total Completed & Stored to DateAdd up total work completed + stored materials from G703.
RetainagePercentage withheld (e.g., 10% of Total Completed & Stored).
Total Earned Less Retainage(Total Completed & Stored) – (Retainage).
Less Previous PaymentsEnter the amount already paid in past applications.
Current Payment Due(Total Earned Less Retainage) – (Previous Payments).
Balance to Finish(Total Contract Sum to Date) – (Total Completed & Stored).

📍 Section 3: Certification & Signatures

Contractor’s Signature → Required before submission.
Architect’s Certification → The architect (or project owner) must sign to approve the payment.


📝 Step 2: Filling Out the G703 Form (Continuation Sheet)

The G703 Continuation Sheet provides a line-item breakdown of work completed, previous billings, and remaining balance.


📍 Section 1: General Information

Project Name & Number → Same as the G702 form.
Contractor Name → Your company name.
Application Number & Date → Same as G702.


📍 Section 2: Line-Item Breakdown (Work Completed)

Each line item corresponds to a specific scope of work, matching the Schedule of Values from the contract.

ColumnWhat to Enter
A – Item No.Assign a sequential number to each work category.
B – Description of WorkList work activities (e.g., “Foundation”, “Framing”, “Electrical”, etc.).
C – Scheduled ValueThe total cost assigned to that item in the contract.
D – Work Completed (This Period)Amount billed for work completed during this pay cycle.
E – Work Completed (Previous Periods)Total of all amounts previously billed for this work item.
F – Total Completed & Stored to Date(D) + (E) – This is the cumulative total.
G – % Complete(F) ÷ (C) × 100 – Shows project progress.
H – Balance to Finish(C) – (F) – The remaining amount for this line item.
I – RetainageAmount withheld (e.g., 10% of F).

📍 Step 3: Review & Submit

🔍 Double-check calculations → Ensure all totals align between G702 & G703.
✍️ Sign G702 → The contractor must sign before submission.
📩 Submit to the owner or architect → For approval before payment processing.


🔹 Example Scenario

Project: ABC Commercial Building

Item No.Description of WorkScheduled ValueWork Completed (This Period)Work Completed (Previous Periods)Total Completed & Stored% CompleteBalance to FinishRetainage (10%)
1Site Work$100,000$10,000$50,000$60,00060%$40,000$6,000
2Foundation$200,000$50,000$100,000$150,00075%$50,000$15,000
3Framing$300,000$80,000$50,000$130,00043%$170,000$13,000

✅ Key Takeaways

G702 provides a high-level summary of the payment request.
G703 breaks down the work in detail to support the payment application.
Always check for missing signatures, incorrect retainage, or calculation errors before submission.
Submit these forms regularly (monthly or per contract terms) to maintain consistent cash flow.