Ganarpro can Calculate a Civil Scope (Utilities, Drainage, Paving) pricing estimate, prepared using the 2025 North American Pricing Model. We do apply the best-price-wins methodology with Market-Win pricing. Our scopes normally include trenching, storm drainage, domestic water/sewer utilities, concrete and asphalt paving, and site grading. Also include optional line items for trench backfill, erosion control, survey/as-builts, testing, and temporary utility setup. Factor in ADA compliance (ramps, domes)

We can handle the entire quoting process for Ganarpro projects, including bid invitations from your inbox. We’ll create and submit the quote and proposal directly to the general contractor on your behalf — or, if you prefer, we can show you how to do it yourself using Ganarpro.

As of May 2025, we’ve transitioned away from static, one-size-fits-all templates. With our software, scope of work and pricing are now dynamically generated using AI—customized for each project based on its name, type, location, and unique details


Project: NYC H+H Ambulatory & Primary Care Center
Address: 2601 Ocean Parkway, Brooklyn, NY
Size: 27,837 sq. ft.
Bid Strategy: Market-Win (lowest-tier labor and material)
Notes: Union | PLA | Tax-Exempt | TPM Fee Included | ADA Compliance Included

Civil Scope Estimate

Project Area: 71,127 SF
Location: San Diego, CA
Wage Type: Private Project (Non-Prevailing Wage)


Core Scope Items (Required)

Scope ItemQuantity / UnitUnit Cost (Market-Win)Total Cost
1. Trenching (utility runs)1,500 LF$10 / LF$15,000
2. Storm Drainage System1,000 LF (piping + inlets)$30 / LF$30,000
3. Water / Sewer Utilities1,000 LF combined$25 / LF$25,000
4. Concrete Paving (ADA + paths)8,000 SF$6.50 / SF$52,000
5. Asphalt Paving (light duty)5,000 SF$4.75 / SF$23,750
6. Site Grading & Compaction71,127 SF (1.63 ac)$0.75 / SF$53,345
7. ADA Ramps & Truncated Domes6 each$950 / ea$5,700

Subtotal (Core Scope): $204,795


Optional Line Items (Add-On Pricing)

Optional ItemQuantity / UnitUnit CostTotal Cost
1. Trench Backfill (imported fill)1,000 LF$4 / LF$4,000
2. Erosion Control (BMPs)Lump Sum$3,500
3. Survey & As-Built DrawingsLump Sum$3,000
4. Soils Testing / Compaction10 tests$350 / test$3,500
5. Temporary Utility SetupPower + Water ConnectionsLump Sum$5,000

Optional Items Subtotal: $19,000


Summary

CategoryAmount
Core Scope$204,795
Optional Line Items$19,000
Total (Pre-Tax):$223,795
Tax (7.75%)$17,340
Total w/ Tax:$241,135

Proposal Notes

  • Bonding Rate: 2.0% (if required): +$4,823
  • License: Include CA C-34 or A Classification
  • Terms: 30% upon mobilization, balance via progress payments
  • Schedule Impact: Pricing valid for 30 days; assume NTP within 60 days